Curtailment is a contract problem first

The IEA found solar curtailment of about 14% a year in Sumatra and traced it to inflexible contracts, not a lack of wires. What curtailment costs a project, why rooftop quotas exist and how developers can protect revenue as 100 GW of solar arrives.

Download report (PDF)Download data (CSV)
Illustration for Curtailment is a contract problem first

Key points

  • The IEA observed solar curtailment of about 14% a year in Sumatra, tied to inflexible power purchase agreements.
  • It found thermal and hydro fleets could supply the flexibility needed, if contracts allowed it.
  • For a 100 MWp plant, 14% curtailment at the large-solar ceiling costs about USD 1.3 million a year.

When a grid cannot use all the solar power available, the operator tells plants to reduce output. That is curtailment, and for a solar project paid per kWh it is lost revenue. As Indonesia plans tens of gigawatts of solar, curtailment is the risk lenders ask about first.

What the IEA found

The IEA’s review of Indonesia’s power system observed solar curtailment of about 14% a year in Sumatra. Its explanation was not a shortage of transmission. It was contracts: power purchase agreements with thermal plants that oblige PLN to take or pay for minimum volumes, so that in hours of low demand and high sun, solar is the plant that gets turned down.

The IEA’s broader findings were striking:

  • Contract inflexibility also blocks new hydro and geothermal, not only solar, and raises system costs.
  • Indonesia’s thermal and hydro fleets could provide the flexibility needed for higher renewable shares, if contracts let them.
  • No new grid or storage investment was needed to support the plan as it stood then, and Indonesia could aim higher.

What 14% costs a project

One kWh in seven never reaches the grid at 14% curtailmentAnnual output of a 100 MWp solar plant at 1,300 kWh per kWp, GWh
  • Delivered
  • Curtailed
No curtailment130.0130.0 GWh
14% curtailment111.818.2130.0 GWh
Source: Satu Energy calculation using the IEA’s Sumatra curtailment rateDownload CSVSatu Energy
Show data
ItemDeliveredCurtailed
No curtailment130.00.0
14% curtailment111.818.2
Curtailment can wipe out a project’s marginRevenue lost each year by a 100 MWp plant at 6.95 US cents per kWh, USD million
14% curtailment 1.26 USD m
10% curtailment 0.90 USD m
5% curtailment 0.45 USD m
2% curtailment 0.18 USD m
Source: Satu Energy calculation at the Perpres 112/2022 large-solar base ceilingDownload CSVSatu Energy
Show data
Curtailment rateUSD m
14% curtailment1.26
10% curtailment0.90
5% curtailment0.45
2% curtailment0.18

Over a 25-year contract, 14% curtailment on a 100 MWp plant is more than USD 30 million of lost revenue before discounting, on a project that costs in the order of USD 70 million to build. Few financial models survive that unless the contract compensates for it.

Why rooftop solar has quotas

The same logic explains PLN’s rooftop quotas. Under the 2024 rules, each grid system has a yearly rooftop allowance. The allocation shows where PLN thinks the grid can absorb solar and where it cannot:

Most rooftop quota goes to the strong Java gridRooftop solar quota allocation by grid region, MW
Java, Madura, Bali 1,400 MW
Kalimantan 89 MW
Sumatra 80 MW
Sulawesi 17 MW
Maluku, Papua, Nusa Tenggara 7 MW

Allocation for the quota period as reported; yearly national totals rise from 901 MW in 2024 to 1,593 MW in 2028.

Source: EnergyTrend and IESR, reporting the 2024 quota decreeDownload CSVSatu Energy
Show data
RegionMW
Java, Madura, Bali1,400
Kalimantan89
Sumatra80
Sulawesi17
Maluku, Papua, Nusa Tenggara7

How developers protect revenue

  1. Read the curtailment clause first. Does PLN pay for “deemed energy” when it curtails for reasons other than grid faults? Is there a cap on uncompensated hours?
  2. Model curtailment hourly. Use the system’s demand profile, must-run thermal and other solar in the same area. A monthly model cannot see midday surplus.
  3. Add storage where curtailment is structural. A battery charged with energy that would be curtailed has near-zero fuel cost, which changes its economics.
  4. Pick the grid, not just the sun. A site on a strong 150 kV node near demand will be curtailed less than a better-irradiated site at the end of a weak line.

What would reduce it system-wide

Renegotiating take-or-pay terms, paying thermal plants for flexibility instead of energy, faster growth in daytime demand, and storage. Rising demand helps: Indonesia’s consumption per person rose 12% in 2025, which creates daytime room for solar each year.

What to watch

  • Curtailment and deemed-energy terms in Mentari Nusantara contracts.
  • Any PLN programme to retrofit coal plants for lower minimum load.
  • Storage requirements in solar tenders outside Java.

Sources

  1. IEA, Enhancing Indonesia’s Power System, executive summary
  2. IEA, closing workshop presentation on Indonesia’s power system
  3. IESR, flexibility in power system development
  4. EnergyTrend, Indonesia issues new quota for rooftop solar
  5. IESR, efforts to encourage rooftop solar quota fulfilment

Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.