Curtailment is a contract problem first
The IEA found solar curtailment of about 14% a year in Sumatra and traced it to inflexible contracts, not a lack of wires. What curtailment costs a project, why rooftop quotas exist and how developers can protect revenue as 100 GW of solar arrives.
Key points
- The IEA observed solar curtailment of about 14% a year in Sumatra, tied to inflexible power purchase agreements.
- It found thermal and hydro fleets could supply the flexibility needed, if contracts allowed it.
- For a 100 MWp plant, 14% curtailment at the large-solar ceiling costs about USD 1.3 million a year.
When a grid cannot use all the solar power available, the operator tells plants to reduce output. That is curtailment, and for a solar project paid per kWh it is lost revenue. As Indonesia plans tens of gigawatts of solar, curtailment is the risk lenders ask about first.
What the IEA found
The IEA’s review of Indonesia’s power system observed solar curtailment of about 14% a year in Sumatra. Its explanation was not a shortage of transmission. It was contracts: power purchase agreements with thermal plants that oblige PLN to take or pay for minimum volumes, so that in hours of low demand and high sun, solar is the plant that gets turned down.
The IEA’s broader findings were striking:
- Contract inflexibility also blocks new hydro and geothermal, not only solar, and raises system costs.
- Indonesia’s thermal and hydro fleets could provide the flexibility needed for higher renewable shares, if contracts let them.
- No new grid or storage investment was needed to support the plan as it stood then, and Indonesia could aim higher.
What 14% costs a project
- Delivered
- Curtailed
Show data
| Item | Delivered | Curtailed |
|---|---|---|
| No curtailment | 130.0 | 0.0 |
| 14% curtailment | 111.8 | 18.2 |
Over a 25-year contract, 14% curtailment on a 100 MWp plant is more than USD 30 million of lost revenue before discounting, on a project that costs in the order of USD 70 million to build. Few financial models survive that unless the contract compensates for it.
Why rooftop solar has quotas
The same logic explains PLN’s rooftop quotas. Under the 2024 rules, each grid system has a yearly rooftop allowance. The allocation shows where PLN thinks the grid can absorb solar and where it cannot:
How developers protect revenue
- Read the curtailment clause first. Does PLN pay for “deemed energy” when it curtails for reasons other than grid faults? Is there a cap on uncompensated hours?
- Model curtailment hourly. Use the system’s demand profile, must-run thermal and other solar in the same area. A monthly model cannot see midday surplus.
- Add storage where curtailment is structural. A battery charged with energy that would be curtailed has near-zero fuel cost, which changes its economics.
- Pick the grid, not just the sun. A site on a strong 150 kV node near demand will be curtailed less than a better-irradiated site at the end of a weak line.
What would reduce it system-wide
Renegotiating take-or-pay terms, paying thermal plants for flexibility instead of energy, faster growth in daytime demand, and storage. Rising demand helps: Indonesia’s consumption per person rose 12% in 2025, which creates daytime room for solar each year.
What to watch
- Curtailment and deemed-energy terms in Mentari Nusantara contracts.
- Any PLN programme to retrofit coal plants for lower minimum load.
- Storage requirements in solar tenders outside Java.
Sources
- IEA, Enhancing Indonesia’s Power System, executive summary
- IEA, closing workshop presentation on Indonesia’s power system
- IESR, flexibility in power system development
- EnergyTrend, Indonesia issues new quota for rooftop solar
- IESR, efforts to encourage rooftop solar quota fulfilment
Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.
Satu Energy (PT Satu Solusi Energi), Jakarta. Read online and download the chart data at satuenergy.com/insights/solar-curtailment-indonesia/. Contact: contact@satuenergy.com. This report uses public sources only; figures for plans and programmes are not operating capacity unless stated.