Energy Ministry Regulation 8/2025 requires energy management from industry and transport using 4,000 TOE a year or more and buildings using 500 TOE. In electricity terms that is about 46,500 MWh and 5,800 MWh. What sites must do.
Key points
- Industry and transport using 4,000 TOE a year, and buildings using 500 TOE, must manage energy.
- That is roughly 46,500 MWh and 5,800 MWh of energy a year.
- Sites need an energy manager, an audit every three years and annual reporting.
Regulation 8/2025 of the Ministry of Energy and Mineral Resources took effect on 13 March 2025. It replaces the 2012 rule and implements Government Regulation 33/2023 on energy conservation.
- 4,000 TOEIndustry and transport threshold, about 46,500 MWh
- 500 TOEBuilding threshold, about 5,800 MWh
- 3 yrsInterval between mandatory energy audits
Who must comply
Large energy users must run a formal energy management programme. Reported thresholds are 4,000 TOE a year for industry and transport, and 500 TOE for buildings such as offices, hotels and hospitals. One summary mentions a 6,000 TOE threshold for another category that we could not confirm in the regulation’s text.
A tonne of oil equivalent (TOE) is about 11.63 MWh of energy. Converted:
For a building that runs mostly on electricity, 5,815 MWh a year is an average load of about 660 kW, within reach of large hospitals, malls and hotels.
What they must do
- Appoint an energy manager.
- Audit energy use at least once every three years.
- Implement audit recommendations within three years.
- Report performance to the ministry every year.
Administrative sanctions apply to sites that do not comply.
Where solar fits
An audit usually starts with efficiency: motors, chillers, lighting, compressed air. Once demand is lean, on-site solar sized to the remaining daytime load is often the next measure. Under the 2024 rooftop rules, sizing to load matters even more. Metered data, before and after, is what turns both into reportable savings.
What a 10% saving is worth
For a factory right at the threshold, buying all its energy as electricity at the I-3 tariff, every percentage point of savings is worth more than Rp 500 million a year.
Sources
- Audit Board of Indonesia (BPK), Permen ESDM 8/2025 on Energy Management
- EnergyHub, Driving the implementation of MEMR Regulation 8/2025
- SIP Law Firm, Energy efficiency programme
- TÜV NORD, Whitepaper on energy audits and energy management systems
- Metro TV, electricity tariffs as of 31 August 2026
Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.
Satu Energy (PT Satu Solusi Energi), Jakarta. Read online and download the chart data at satuenergy.com/insights/energy-management-regulation-8-2025/. Contact: contact@satuenergy.com. This report uses public sources only; figures for plans and programmes are not operating capacity unless stated.