Solar and BESS feasibility: seven checks
A practical checklist for solar and battery (BESS) feasibility studies in Indonesia: irradiance data, hourly simulation, losses, DC/AC ratio, battery sizing, grid connection studies and honest financial sensitivity.
Key points
- Use hourly (8,760-hour) simulation for any project with storage or export limits.
- Size the battery from its purpose, not a rule of thumb.
- Run grid connection studies before the bid, not after.
With the 100 GWp programme and Mentari Nusantara tenders under way, many teams must assess dozens of sites quickly. A good feasibility study does not need to be long. It needs to answer one question honestly: should this be built, on what assumptions, and how sensitive is the answer to them.
- 8,760Hours to simulate, not 12 monthly averages
- ~5%Revenue error from a 5% irradiance error
- 7Checks before you bid
1. Irradiance data you can defend
Output scales with irradiance; a 5% error in the resource is close to a 5% error in revenue for 25 years. Use hourly time series from recognised sources such as PVGIS or NASA POWER, compare more than one, and state the uncertainty. For large plants, a few months of on-site measurement pays off with lenders.
2. Hourly simulation, not monthly averages
Monthly averages are fine for a first look. For an investment decision, especially with batteries or export limits, simulate all 8,760 hours. Only then can you see clipping, full batteries and lost energy.
3. Losses, itemised
Final yield is many small losses: temperature, soiling, mismatch, DC and AC cabling, inverter, transformer, availability and degradation. Put them in one table. Hidden loss assumptions cause most disputes between developers, EPCs and lenders.
4. A DC/AC ratio you chose
The ratio of module capacity to inverter or connection capacity sets clipping at midday and gains at the shoulders. The right value depends on module price, tariff, export limit and storage. Compare several, for example 1.1 to 1.4, and choose on project value.
5. Battery size from the system’s need
A BESS can shift energy to the evening, smooth output, provide reserve or avoid curtailment. Each purpose gives a different power (MW) and energy (MWh) size. Set the purpose, then simulate hourly dispatch with the solar plant, including degradation and replacement.
6. Grid connection studies early
Many projects look viable until the connection point is checked. At minimum:
- Load flow: overloads at full output and low load.
- Voltage: rise beyond limits, and reactive power needed.
- Short circuit: fault contribution and short-circuit ratio, which decide grid-forming needs.
- Stability and frequency: critical in small systems where solar is a large share of load.
These often set reinforcement costs. It is also why PLN’s Green Enabling Super Grid matters to every developer.
7. A financial model honest about uncertainty
Report IRR, NPV, LCOE and payback, then their sensitivity to the five drivers that matter most: irradiance, CAPEX, tariff, degradation and cost of capital. Lenders trust a study that shows where a project can fail more than one that shows a single good number.
Why the inputs matter: a worked example
In our factory rooftop example, changing one input at a time moved payback by up to a year and a half:
Checklist
| Area | Key question |
|---|---|
| Irradiance | How many sources, and what uncertainty? |
| Simulation | Are solar and battery simulated hourly? |
| Losses | Is every loss listed and justified? |
| DC/AC | Were several ratios compared? |
| BESS | What is the battery for, and does its size follow? |
| Grid | Were load flow, voltage, fault level and stability checked? |
| Finance | Are there sensitivities and scenarios? |
Most of these steps, from layout to financial model, run in our VRE Integration Studio.
Satu Energy (PT Satu Solusi Energi), Jakarta. Read online and download the chart data at satuenergy.com/insights/solar-bess-feasibility-study-checklist/. Contact: contact@satuenergy.com. This report uses public sources only; figures for plans and programmes are not operating capacity unless stated.