ExplainerEngineering

Solar and BESS feasibility: seven checks

A practical checklist for solar and battery (BESS) feasibility studies in Indonesia: irradiance data, hourly simulation, losses, DC/AC ratio, battery sizing, grid connection studies and honest financial sensitivity.

Download report (PDF)Download data (CSV)
Illustration for Solar and BESS feasibility: seven checks

Key points

  • Use hourly (8,760-hour) simulation for any project with storage or export limits.
  • Size the battery from its purpose, not a rule of thumb.
  • Run grid connection studies before the bid, not after.

With the 100 GWp programme and Mentari Nusantara tenders under way, many teams must assess dozens of sites quickly. A good feasibility study does not need to be long. It needs to answer one question honestly: should this be built, on what assumptions, and how sensitive is the answer to them.

The checklist in three numbers
  • 8,760Hours to simulate, not 12 monthly averages
  • ~5%Revenue error from a 5% irradiance error
  • 7Checks before you bid
Source: Satu EnergyDownload CSVSatu Energy

1. Irradiance data you can defend

Output scales with irradiance; a 5% error in the resource is close to a 5% error in revenue for 25 years. Use hourly time series from recognised sources such as PVGIS or NASA POWER, compare more than one, and state the uncertainty. For large plants, a few months of on-site measurement pays off with lenders.

2. Hourly simulation, not monthly averages

Even near the equator, the best month yields over a third more than the worstExample: 500 kWp rooftop in Surabaya, energy by month, MWh
Jan 51 MWh
Feb 49 MWh
Mar 56 MWh
Apr 58 MWh
May 60 MWh
Jun 58 MWh
Jul 63 MWh
Aug 67 MWh
Sep 67 MWh
Oct 66 MWh
Nov 55 MWh
Dec 50 MWh

An illustrative project, not a measured plant. 700 MWh a year, 1,400 kWh/kWp.

Source: Satu Energy example, 8,760-hour satu.solar simulationDownload CSVSatu Energy
Show data
MonthMWh
Jan51
Feb49
Mar56
Apr58
May60
Jun58
Jul63
Aug67
Sep67
Oct66
Nov55
Dec50

Monthly averages are fine for a first look. For an investment decision, especially with batteries or export limits, simulate all 8,760 hours. Only then can you see clipping, full batteries and lost energy.

3. Losses, itemised

Final yield is many small losses: temperature, soiling, mismatch, DC and AC cabling, inverter, transformer, availability and degradation. Put them in one table. Hidden loss assumptions cause most disputes between developers, EPCs and lenders.

4. A DC/AC ratio you chose

The ratio of module capacity to inverter or connection capacity sets clipping at midday and gains at the shoulders. The right value depends on module price, tariff, export limit and storage. Compare several, for example 1.1 to 1.4, and choose on project value.

5. Battery size from the system’s need

A BESS can shift energy to the evening, smooth output, provide reserve or avoid curtailment. Each purpose gives a different power (MW) and energy (MWh) size. Set the purpose, then simulate hourly dispatch with the solar plant, including degradation and replacement.

6. Grid connection studies early

Many projects look viable until the connection point is checked. At minimum:

  • Load flow: overloads at full output and low load.
  • Voltage: rise beyond limits, and reactive power needed.
  • Short circuit: fault contribution and short-circuit ratio, which decide grid-forming needs.
  • Stability and frequency: critical in small systems where solar is a large share of load.

These often set reinforcement costs. It is also why PLN’s Green Enabling Super Grid matters to every developer.

7. A financial model honest about uncertainty

Report IRR, NPV, LCOE and payback, then their sensitivity to the five drivers that matter most: irradiance, CAPEX, tariff, degradation and cost of capital. Lenders trust a study that shows where a project can fail more than one that shows a single good number.

Why the inputs matter: a worked example

In our factory rooftop example, changing one input at a time moved payback by up to a year and a half:

Cost and yield assumptions move payback the mostSimple payback for a 500 kWp roof in Surabaya, years
Installed cost +18% 9.3 yrs
Yield −8% (Jakarta) 8.5 yrs
Base case 7.7 yrs
Yield +18% (Kupang) 6.5 yrs
Installed cost −18% 6.2 yrs
Source: Satu Energy worked exampleDownload CSVSatu Energy
Show data
Scenarioyrs
Installed cost +18%9.3
Yield −8% (Jakarta)8.5
Base case7.7
Yield +18% (Kupang)6.5
Installed cost −18%6.2

Checklist

AreaKey question
IrradianceHow many sources, and what uncertainty?
SimulationAre solar and battery simulated hourly?
LossesIs every loss listed and justified?
DC/ACWere several ratios compared?
BESSWhat is the battery for, and does its size follow?
GridWere load flow, voltage, fault level and stability checked?
FinanceAre there sensitivities and scenarios?

Most of these steps, from layout to financial model, run in our VRE Integration Studio.