Indonesia’s 100 GWp solar programme, explained
Where the PLTS 100 GWp programme stands in November 2026: 14 launch projects totalling 5.3 GWp, six projects worth 4.55 GWp ready for tender, and the technical factors that decide which projects get built.
Key points
- 14 launch projects add up to 5.3 GWp, about 5% of the 100 GWp target.
- Six projects worth 4.55 GWp are listed as ready for tender, starting with Mentari Nusantara I.
- Grid, land and storage readiness, not panels, will decide the pace.
On 25 August 2026, President Prabowo Subianto launched the 100 GWp solar programme (PLTS 100 GWp) at the Gilimanuk solar site in Jembrana, Bali. The target is explicit: 100 GWp within three years. For developers, EPCs and landowners, the useful questions are narrower. Which projects have taken shape, how they will be procured, and what decides whether they connect.
- 100 GWpTarget, within three years of the August 2026 launch
- 5.3 GWpIn the 14 launch projects
- 4.55 GWpListed as ready for tender
- 1,225 MWTendered so far, in Mentari Nusantara I
The official numbers
According to the Cabinet Secretariat, the programme starts with 14 solar plants totalling 5.3 GWp in six provinces:
| Province | Sites |
|---|---|
| Riau Islands | Tembesi, Sembur Island |
| Bangka Belitung Islands | Rengit Island |
| West Java | Saguling, Purwakarta, Jatiluhur, Cirata, Jatigede |
| Central Java | Gajah Mungkur Reservoir |
| East Java | Karangkates, Madura, Pasuruan, Banyuwangi |
| Bali | Gilimanuk |
The energy ministry named four capacities: Gilimanuk 300 MWp, Gajah Mungkur floating solar 134 MWp, Sembur village 0.92 MWp and Rengit Island 0.078 MWp. The range is deliberate: utility plants on the main grid sit beside small systems that replace diesel.
The small end shows the benefit plainly. On Rengit Island, supply went from about 12 to 24 hours a day and the cost of supply fell by about IDR 4,400/kWh, or 26%.
Nationally, Energy Minister Bahlil Lahadalia put the investment at about US$73 billion, with subsidy savings of IDR 73.9 trillion a year from less diesel generation and about 5.52 million cumulative jobs.
Ready for tender: 4.55 GWp
As of 20 October 2026, the government listed six projects totalling about 4,548.92 MWp as ready for procurement:
- Jatiluhur floating solar
- Cirata floating solar
- Jatigede floating solar
- Madura cluster solar plus BESS
- Gilimanuk solar, Bali
- Solar on Land Bank (Bank Tanah) land in Purwakarta
PLN says tenders will follow in stages, by project readiness, starting with Mentari Nusantara I, and that delivery is aligned with land, grid and supporting infrastructure readiness. That last phrase is the heart of the programme.
GWp is not GW
The programme counts GWp, the peak DC rating of the modules. Grid-side AC capacity is lower, depending on the DC/AC ratio, typically 1.1 to 1.4 for utility solar. When comparing tenders, RUPTL figures and announcements, check the unit first.
A scheme still taking shape
The 100 GW idea was first framed around villages, through the Koperasi Desa Merah Putih cooperatives. Through 2026 the approach shifted toward a staged start in areas that already have distribution infrastructure, while regulations are prepared. Meanwhile PLN’s RUPTL 2025–2034 includes about 17 GW of new solar over the decade. Read utility tenders and village-scale schemes as two separate tracks.
What decides which projects get built
- Grid capacity at the connection point. Hundreds of MWp at one substation change power flows. Load-flow, short-circuit and stability studies decide reinforcement, and who pays.
- Batteries. Many sites are paired with BESS. Battery size decides whether solar only saves daytime fuel or also serves the evening peak.
- Reservoir sites. At least five of the fourteen launch sites are reservoirs: Saguling, Cirata, Jatiluhur, Jatigede and Gajah Mungkur. Floating solar brings mooring, water-level and hydro-coordination questions.
- Land and permits. PLN names land readiness as a condition; using Land Bank sites is one way to cut that risk.
- Consistent assumptions. Across a portfolio, one consistent model matters more than a complicated one.
The pace problem in one chart
Three years for 100 GWp means about 33 GWp a year. Indonesia has never built anything close to that. PLN added 458 MW of solar in the whole of 2021–2025, and the country’s module factories can make about 10.9 GW a year.
Mixed units: the target and project lists in GWp, the tender in MW (AC).
Show data
| Stage | GW |
|---|---|
| Programme target | 100 |
| Launch projects | 5.3 |
| Ready for tender | 4.55 |
| Tendered (Mentari Nusantara I) | 1.225 |
What would make the pace credible is not a larger target but a pipeline: grid connection studies done before tender, land secured, storage specified and standard contracts reused from one bundle to the next. Each Mentari phase is the test.
The output, if built, would be large. At Indonesian yields of about 1,300–1,400 kWh per kWp, 100 GWp produces in the order of 130–140 TWh a year, roughly a quarter of national consumption in 2025.
What to watch
- Tender dates for the five projects after Mentari Nusantara I.
- A RUPTL update that reflects the 100 GWp target.
- Rules for village and cooperative solar.
- Physical progress. West Java’s deputy governor cited Saguling floating solar at 47%; consistent project-level updates are not yet published.
Sources
- Cabinet Secretariat of Indonesia, launch of the 100 GWp solar programme, 25 August 2026
- Ministry of Energy and Mineral Resources, from Gilimanuk to Pulau Rengit, August 2026
- Kontan, PLN refines procurement for PLTS 100 GWp, 20 October 2026
- Bloomberg Technoz, village solar under the 100 GW programme enters PLN data synchronisation
- Warta Ekonomi, Saguling floating solar joins the programme at 47% progress
- APAMSI via Ecobiz Asia, Indonesia’s solar manufacturing capacity reaches 10.9 GW
- Katadata, PLN outlines six renewable projects at COP31
Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.