Mentari Nusantara I, II and III: PLN’s solar tenders

Status of PLN’s Mentari Nusantara solar tenders in November 2026: Mentari I at 1,225 MW across six regions with a 2029 COD target, Mentari II at about 1.9 GWp to be launched, and what is known about phase III.

Download report (PDF)Download data (CSV)
Illustration for Mentari Nusantara I, II and III: PLN’s solar tenders

Key points

  • Mentari Nusantara I: 1,225 MW across six regions, tender opened 30 April 2026, COD target 2029.
  • Java takes almost half; Maluku, Papua and NTB together take 200 MW.
  • Mentari II (about 1.9 GWp) is next. Phase III has not been announced.

Mentari Nusantara is PLN’s series of bundled utility-scale solar tenders, and the first procurement under the national solar push. Capacities are reported differently in different places, so here is a single view, with the mismatches called out.

Mentari Nusantara at a glance
  • 1,225 MWMentari I, tendered 30 April 2026
  • 49%Share of Mentari I in Java
  • ~1.9 GWpMentari II, to be launched
  • 2029COD target for Mentari I
Source: PLN via Bisnis.com, ANTARA, Katadata, 2026Download CSVSatu Energy

Summary as of 15 November 2026

PhaseReported capacityStatus
Mentari Nusantara I1,225 MW (tender, May 2026); 1,743 MWp (PLN at COP31)Tender launched 30 April 2026, COD target 2029
Mentari Nusantara II1,965 MWp (Katadata); 1.9 GW (CNBC Indonesia)To be launched in 2026
Mentari Nusantara IIINo official figureNo public announcement we could verify

Mentari Nusantara I

Java takes almost half of Mentari Nusantara ITendered capacity by region, MW
Java 600 MW
Kalimantan 340 MW
Maluku and Papua 120 MW
West Nusa Tenggara 80 MW
Sulawesi 50 MW
Sumatra 35 MW
Source: PLN via Bisnis.com and ANTARA, May 2026Download CSVSatu Energy
Show data
RegionMW
Java600
Kalimantan340
Maluku and Papua120
West Nusa Tenggara80
Sulawesi50
Sumatra35

PLN launched the tender on 30 April 2026 through GIGA ONE, an integrated procurement that bundles many solar sites into one package. PLN says this makes projects more bankable and speeds them from procurement to construction.

RegionCapacity
Java600 MW
Kalimantan340 MW
Maluku and Papua120 MW
West Nusa Tenggara80 MW
Sulawesi50 MW
Sumatra35 MW
Total1,225 MW

All units target commercial operation in 2029.

On 20 July 2026, PLN and Danantara Indonesia held a market consultation. Secondary reporting describes about 1 GW with a 1,165 MW quota across seven regions, with winners forming a project company per site, possibly with a PLN subsidiary, and signing a PPA with PLN. We have not seen this in a PLN release; treat it as indicative.

On 10 November 2026, at the Indonesia Pavilion at COP31, PLN director Edwin Nugraha Putra presented Mentari Nusantara I at 1,743 MWp and described it as launched.

Why 1,225 MW and 1,743 MWp can both be right

Most likely, units. MW in a tender usually means grid-side AC capacity; MWp is the modules’ peak DC rating. The ratio, about 1.42, is plausible for tropical utility solar, especially with storage. PLN has not explained the gap, so bid on the definitions in the procurement documents, not on press figures.

Mentari Nusantara II

Mentari II appears in the six projects PLN presented at COP31, part of 10.23 GW to be launched for contracting in 2026. Katadata reports 1,965 MWp; CNBC Indonesia lists 1.9 GW as “PLTS Nusantara 2”. There are no public details yet on regions, procurement scheme or COD. GIGA ONE bundling may be reused; that is our expectation, not PLN’s statement. See the full 10.23 GW list.

Mentari Nusantara III

As of 15 November 2026 we found no official announcement or verifiable reporting on Mentari Nusantara III. If the series continues, the next phase may draw on the 100 GWp projects already listed as ready for tender, such as the Jatiluhur, Cirata and Jatigede floating sites or the Madura solar-plus-BESS cluster. That is our reading. We will update this article when PLN announces it.

MW or MWp: the same tender, two numbers

The DC rating is 42% above the AC tender figureMentari Nusantara I capacity as reported
  • Tender (MW, AC)
  • COP31 (MWp, DC)
Mentari Nusantara I1,225 → 1,743
Source: Bisnis.com (May 2026); Katadata (November 2026)Download CSVSatu Energy
Show data
ItemTender (MW, AC)COP31 (MWp, DC)
Mentari Nusantara I1,2251,743

What a bundled tender changes

GIGA ONE bundles many sites into one procurement. For bidders that means one set of documents, one evaluation and, if PLN reuses the template, faster repeat phases. It also raises the bar: a bidder must prepare sites in regions as different as Java and Papua at once. Small systems in Maluku, Papua and Nusa Tenggara need storage and grid-forming capability that Java sites do not, and those requirements will decide the cost of the bundle.

Curtailment and deemed-energy terms in the contract matter as much as the tariff. See curtailment is a contract problem first.

How bidders prepare

Bundled tenders move technical work forward. Serious teams usually have, before the documents arrive:

  • Screened sites by region on irradiance and land.
  • Checked the grid near each connection point. In small systems in Maluku, Papua and NTB, solar can be a large share of load, so frequency and storage matter more than in Java.
  • Fixed one set of assumptions across sites: irradiance, losses, degradation, availability, DC/AC ratio.
  • Built a financial model that changes fast, because tariffs, local content and ownership can move mid-process.

Sources

  1. Kontan, PLN refines procurement for PLTS 100 GWp, tenders in stages, 20 October 2026
  2. Bisnis.com, PLN tenders 1.22 GW Mentari Nusantara solar, operating by 2029
  3. ANTARA, PLN launches Mentari Nusantara I through GIGA ONE integrated procurement
  4. Metadaya, Mentari Nusantara I market consultation with Danantara, July 2026
  5. Katadata, PLN outlines six renewable projects at COP31, 11 November 2026
  6. CNBC Indonesia, PLN ready to launch 10.23 GW of new renewable contracts, 11 November 2026

Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.