Mentari Nusantara I, II and III: PLN’s solar tenders
Status of PLN’s Mentari Nusantara solar tenders in November 2026: Mentari I at 1,225 MW across six regions with a 2029 COD target, Mentari II at about 1.9 GWp to be launched, and what is known about phase III.
Key points
- Mentari Nusantara I: 1,225 MW across six regions, tender opened 30 April 2026, COD target 2029.
- Java takes almost half; Maluku, Papua and NTB together take 200 MW.
- Mentari II (about 1.9 GWp) is next. Phase III has not been announced.
Mentari Nusantara is PLN’s series of bundled utility-scale solar tenders, and the first procurement under the national solar push. Capacities are reported differently in different places, so here is a single view, with the mismatches called out.
- 1,225 MWMentari I, tendered 30 April 2026
- 49%Share of Mentari I in Java
- ~1.9 GWpMentari II, to be launched
- 2029COD target for Mentari I
Summary as of 15 November 2026
| Phase | Reported capacity | Status |
|---|---|---|
| Mentari Nusantara I | 1,225 MW (tender, May 2026); 1,743 MWp (PLN at COP31) | Tender launched 30 April 2026, COD target 2029 |
| Mentari Nusantara II | 1,965 MWp (Katadata); 1.9 GW (CNBC Indonesia) | To be launched in 2026 |
| Mentari Nusantara III | No official figure | No public announcement we could verify |
Mentari Nusantara I
PLN launched the tender on 30 April 2026 through GIGA ONE, an integrated procurement that bundles many solar sites into one package. PLN says this makes projects more bankable and speeds them from procurement to construction.
| Region | Capacity |
|---|---|
| Java | 600 MW |
| Kalimantan | 340 MW |
| Maluku and Papua | 120 MW |
| West Nusa Tenggara | 80 MW |
| Sulawesi | 50 MW |
| Sumatra | 35 MW |
| Total | 1,225 MW |
All units target commercial operation in 2029.
On 20 July 2026, PLN and Danantara Indonesia held a market consultation. Secondary reporting describes about 1 GW with a 1,165 MW quota across seven regions, with winners forming a project company per site, possibly with a PLN subsidiary, and signing a PPA with PLN. We have not seen this in a PLN release; treat it as indicative.
On 10 November 2026, at the Indonesia Pavilion at COP31, PLN director Edwin Nugraha Putra presented Mentari Nusantara I at 1,743 MWp and described it as launched.
Why 1,225 MW and 1,743 MWp can both be right
Most likely, units. MW in a tender usually means grid-side AC capacity; MWp is the modules’ peak DC rating. The ratio, about 1.42, is plausible for tropical utility solar, especially with storage. PLN has not explained the gap, so bid on the definitions in the procurement documents, not on press figures.
Mentari Nusantara II
Mentari II appears in the six projects PLN presented at COP31, part of 10.23 GW to be launched for contracting in 2026. Katadata reports 1,965 MWp; CNBC Indonesia lists 1.9 GW as “PLTS Nusantara 2”. There are no public details yet on regions, procurement scheme or COD. GIGA ONE bundling may be reused; that is our expectation, not PLN’s statement. See the full 10.23 GW list.
Mentari Nusantara III
As of 15 November 2026 we found no official announcement or verifiable reporting on Mentari Nusantara III. If the series continues, the next phase may draw on the 100 GWp projects already listed as ready for tender, such as the Jatiluhur, Cirata and Jatigede floating sites or the Madura solar-plus-BESS cluster. That is our reading. We will update this article when PLN announces it.
MW or MWp: the same tender, two numbers
- Tender (MW, AC)
- COP31 (MWp, DC)
Show data
| Item | Tender (MW, AC) | COP31 (MWp, DC) |
|---|---|---|
| Mentari Nusantara I | 1,225 | 1,743 |
What a bundled tender changes
GIGA ONE bundles many sites into one procurement. For bidders that means one set of documents, one evaluation and, if PLN reuses the template, faster repeat phases. It also raises the bar: a bidder must prepare sites in regions as different as Java and Papua at once. Small systems in Maluku, Papua and Nusa Tenggara need storage and grid-forming capability that Java sites do not, and those requirements will decide the cost of the bundle.
Curtailment and deemed-energy terms in the contract matter as much as the tariff. See curtailment is a contract problem first.
How bidders prepare
Bundled tenders move technical work forward. Serious teams usually have, before the documents arrive:
- Screened sites by region on irradiance and land.
- Checked the grid near each connection point. In small systems in Maluku, Papua and NTB, solar can be a large share of load, so frequency and storage matter more than in Java.
- Fixed one set of assumptions across sites: irradiance, losses, degradation, availability, DC/AC ratio.
- Built a financial model that changes fast, because tariffs, local content and ownership can move mid-process.
Sources
- Kontan, PLN refines procurement for PLTS 100 GWp, tenders in stages, 20 October 2026
- Bisnis.com, PLN tenders 1.22 GW Mentari Nusantara solar, operating by 2029
- ANTARA, PLN launches Mentari Nusantara I through GIGA ONE integrated procurement
- Metadaya, Mentari Nusantara I market consultation with Danantara, July 2026
- Katadata, PLN outlines six renewable projects at COP31, 11 November 2026
- CNBC Indonesia, PLN ready to launch 10.23 GW of new renewable contracts, 11 November 2026
Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.