PLN’s 10.23 GW renewable pipeline

At COP31, PLN said it will launch 10.23 GW of renewable projects for contracting in 2026, including Mentari Nusantara I and II, the Bayu Nusantara wind project and three hydro plants, plus a carbon-credit deal with Norway.

Download report (PDF)Download data (CSV)
Illustration for PLN’s 10.23 GW renewable pipeline

Key points

  • PLN plans to launch 10.23 GW of renewables for contracting in 2026.
  • Hydro is half the list; the two Mentari solar phases add about 3.7 GWp.
  • That is nearly five times the 2.1 GW PLN added in 2021–2025.

On 10 November 2026, at the Indonesia Pavilion at COP31 in Antalya, PLN’s Director of Technology, Engineering and Sustainability, Edwin Nugraha Putra, said PLN is ready to launch 10.23 GW of renewable projects for contracting in 2026.

The pipeline at a glance
  • 10.23 GWTo be launched for contracting in 2026
  • ~5.2 GWOf it hydro
  • ~3.7 GWpOf it solar, in two Mentari phases
  • 2.1 GWRenewables PLN added in all of 2021–2025
Source: PLN at COP31 via Katadata, November 2026Download CSVSatu Energy

The six projects

Hydro is half of PLN’s 2026 contracting listProjects presented at COP31, MW (solar in MWp)
  • Hydro
  • Solar
  • Wind
Sulawesi hydro 3,200 MW
Mentari Nusantara II 1,965 MW
Mentari Nusantara I 1,743 MW
Bayu Nusantara 1,275 MW
Sumatra hydro 1,071 MW
Kalimantan hydro 975 MW
Source: PLN at COP31 via Katadata, 11 Nov 2026Download CSVSatu Energy
Show data
ProjectMW
Sulawesi hydro3,200
Mentari Nusantara II1,965
Mentari Nusantara I1,743
Bayu Nusantara1,275
Sumatra hydro1,071
Kalimantan hydro975

As reported by Katadata:

ProjectTypeCapacityStatus
Mentari Nusantara ISolar1,743 MWpLaunched
Mentari Nusantara IISolar1,965 MWpTo be launched
Bayu NusantaraWind1,275 MWTo be launched
Sumatra hydroHydro1,071 MWTo be launched
Kalimantan hydroHydro975 MWTo be launched
Sulawesi hydroHydro3,200 MWTo be launched

These add up to about 10.23 GW, with the two solar projects counted in MWp (DC) and the rest in MW.

CNBC Indonesia lists a different breakdown: Mentari 1 at 1.72 GW, “Nusantara 2” at 1.9 GW, wind at 1.2 GW, Kalimantan hydro at 1 GW and two Sumatra hydro plants at 1 GW and 3 GW. That list sums to 9.82 GW, not the 10.23 GW quoted. Until PLN publishes a document, we treat Katadata’s list as more consistent, but the location of the largest hydro plant is unconfirmed.

From 2.1 GW to 10 GW

Solar was about a fifth of PLN’s renewable additions in 2021–2025Renewable capacity added 2021–2025, MW
  • Hydro
  • Solar
  • Geothermal
  • Bioenergy
Hydro 1,100 MW
Solar 458.1 MW
Geothermal 346.7 MW
Bioenergy 168.1 MW
Source: PLN at COP31 via Katadata, 11 Nov 2026Download CSVSatu Energy
Show data
TechnologyMW
Hydro1,100
Solar458.1
Geothermal346.7
Bioenergy168.1

PLN said it added about 2.1 GW of renewables in 2021–2025: roughly 1.1 GW hydro, 458.1 MW solar, 346.7 MW geothermal and 168.1 MW bioenergy. One year of planned contracting is nearly five times the previous five years of additions. Contracts are not operation, but the step change is clear.

Finance and carbon credits

PLN reported about US$2.94 billion in financing since COP30 from the World Bank, KfW, ADB, AFD, Export Finance Australia and JICA.

It also planned to sign a Mitigation Outcome Purchase Agreement (MOPA) with Norway at COP31, letting PLN sell carbon credits. Volumes differ by source: about 12 million tonnes of CO2 to 2040 (Katadata) or up to 5 million tonnes CO2e (CNBC Indonesia). For developers, watch how PPAs allocate environmental attributes such as carbon credits and RECs.

The mix by technology

Half the pipeline is hydroPLN’s 2026 contracting list by technology, MW
  • Hydro
  • Solar (MWp)
  • Wind
2026 pipeline5,2463,7081,27510,229 MW
Source: PLN at COP31 via Katadata; sums by Satu EnergyDownload CSVSatu Energy
Show data
ItemHydroSolar (MWp)Wind
2026 pipeline5,2463,7081,275

Update: the Norway deal was signed

On 12 November 2026 the Global Green Growth Institute, for Norway, and PLN signed the carbon-credit agreement: up to 12 million tonnes of CO₂ credits from PLN solar projects over about ten years, at a reported USD 20 to 40 per tonne, under Article 6.2. See our analysis of the deal.

What we are watching

  • Hydro is the largest share, about 5.2 GW, with long development cycles.
  • A gigawatt-scale wind project. Bayu Nusantara would be far larger than any wind farm now operating in Indonesia.
  • Solar is the fastest to build. The two Mentari phases, about 3.7 GWp, are the first test of bundled procurement. See the Mentari Nusantara guide.
  • The grid decides timing. Most projects sit far from Java’s load, tying them to the Green Enabling Super Grid.

Sources

  1. Katadata, PLN outlines six renewable projects at COP31, ready to sell carbon credits, 11 November 2026
  2. CNBC Indonesia, PLN ready to launch 10.23 GW of new renewable contracts, 11 November 2026
  3. Katadata, Indonesia–Norway carbon cooperation through PLTS 100 GWp
  4. pv magazine, Norway enters carbon credit agreement with Indonesia

Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.