ReportPolicy

Solar for 80,000 village cooperatives

The plan to put solar on Indonesia’s 80,081 Koperasi Desa Merah Putih began as 100 GW and has been narrowed to a first 13 GW where distribution already exists. What the numbers imply for cost, batteries and the grid.

Download report (PDF)Download data (CSV)
Illustration for Solar for 80,000 village cooperatives

Key points

  • The original plan put about 1 MW of solar in each of 80,000 villages plus 20 GW at district level.
  • The government has narrowed it to a first 13 GW in areas that already have distribution networks.
  • At an analyst estimate of Rp 15 billion per MW, 13 GW is roughly Rp 195 trillion of investment.

In August 2025, energy minister Bahlil Lahadalia announced roughly 100 GW of solar for Indonesia’s new village cooperatives, the Koperasi Desa Merah Putih. There are 80,081 of them. The idea is simple to state: one solar plant per village, owned or operated through the cooperative, supplying local power and income. A year later the plan has been reshaped by arithmetic.

How 100 GW was meant to divide

Katadata reported the original split: 80 GW in villages, about 1 MW in each of 80,000, plus 20 GW at district and city level. IESR described the village model as 1 MW of solar and 4 MW of batteries per village. ICRES’s chair calculated that 100 GW across 80,000 cooperatives is about 1.2 MW each.

Four-fifths of the original plan sat in villagesOriginal split of the cooperative solar plan, GW
  • Villages, ~1 MW each
  • Districts and cities
Original plan8020100 GW
Source: Katadata, 2026Download CSVSatu Energy
Show data
ItemVillages, ~1 MW eachDistricts and cities
Original plan8020

Now: 13 GW first, where the grid already reaches

The government has since decided to build 13 GW first, in areas that already have electricity distribution infrastructure. Bloomberg Technoz reported that projects have entered a data-synchronisation phase with PLN, matching sites to feeders.

The first phase is about an eighth of the headlineVillage cooperative solar, GW
0255075100
100Headline plan
13First phase
Source: Tempo; Katadata, 2026Download CSVSatu Energy
Show data
PlanGW
Headline plan100
First phase13

This is the right correction. A 1 MW plant on a rural 20 kV feeder that peaks at a few hundred kilowatts will push voltage out of limits at midday and back-feed the substation. Starting where the network can absorb the output avoids building stranded assets.

What it would cost

Putra Adhiguna of Energy Shift estimated about Rp 15 billion per MW. That figure reflects small, distributed plants, which cost more per MW than utility-scale farms, and its battery assumption is not stated.

Even the first phase is a Rp 195 trillion programmeInvestment at Rp 15 billion per MW, Rp trillion
First phase, 13 GW 195 Rp tn
Village share of original plan, 80 GW 1,200 Rp tn
Full plan, 100 GW 1,500 Rp tn

Illustrative. Actual cost depends on battery size, site and procurement scale.

Source: Satu Energy calculation from the Energy Shift estimate of Rp 15 billion per MWDownload CSVSatu Energy
Show data
ScopeRp tn
First phase, 13 GW195
Village share of original plan, 80 GW1,200
Full plan, 100 GW1,500

For scale, Rp 195 trillion is larger than the entire 2026 electricity subsidy budget of about Rp 100.8 trillion.

Three engineering questions that decide the outcome

  1. Feeder hosting capacity. Each village plant must be checked against its feeder’s minimum daytime load, voltage limits and protection settings. Thousands of small studies are slower than one large one; a standard screening method is essential.
  2. Battery sizing. A battery that shifts midday output into the evening makes a village plant useful for households, whose demand peaks after dark. A 4:1 battery-to-solar ratio, as in IESR’s framing, is expensive; a smaller battery sized to the village’s evening peak may serve better.
  3. Operations. A cooperative will not employ an O&M team. Remote monitoring across thousands of sites, with alarms and performance ratios, is what keeps small plants producing for 25 years. Without it, faults go unnoticed and output decays.

Who owns the power

The governance question is still open. If PLN buys the output, tariff and contract terms decide whether cooperatives earn anything. If cooperatives sell directly to members, the rules on electricity retail apply. Regulations are being drafted, and Katadata reported investors beginning to show interest.

What to watch

  • The regulation defining ownership, tariffs and PLN’s role.
  • The first tender or allocation of the 13 GW and its unit size.
  • Whether a standard technical package (inverter, battery, monitoring) is mandated for all sites.

Sources

  1. Tempo, energy minister announces 100 GW solar plan for village cooperatives
  2. IESR, realizing one village, one megawatt of solar energy
  3. Katadata, the big solar dream under Koperasi Desa Merah Putih
  4. Kompas, government plans 100 GW of solar at 80,000 Kopdes Merah Putih
  5. Bloomberg Technoz, village solar enters PLN data synchronisation
  6. Green Central Banking, Indonesia wants to bring solar to its villages, 12 November 2026

Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.