Indonesia wants to store Asia’s carbon
Indonesia has rules that let it store foreign CO₂ underground, storage estimates running from 80 to 600 gigatonnes and one flagship project at Tangguh. What is real, what is still a memorandum, and what it means for coal and renewables.
Key points
- Presidential Regulation 14/2024 lets operators reserve up to 30% of storage for CO₂ from abroad.
- Storage estimates range from 80 to 600 gigatonnes, depending on the source and method.
- Several memoranda exist with Japan, Korea and Singapore, but no binding cross-border deals yet.
Indonesia sits on large depleted oil and gas reservoirs and deep saline aquifers. Its neighbours, Singapore, Japan and South Korea, have industries that emit CO₂ and little room to store it. Since 2024, Indonesia has had rules to turn that geography into a business: carbon capture and storage (CCS) as a service.
The rules
Presidential Regulation 14/2024 sets the national CCS framework, and energy ministry Regulation 16/2024 details licensing in designated storage areas. The key commercial rule: operators must reserve at least 70% of storage capacity for domestic CO₂ and may use up to 30% for CO₂ from abroad, from producers that invest in or are affiliated with investments in Indonesia.
- Domestic CO₂, at least
- Foreign CO₂, at most
Show data
| Item | Domestic CO₂, at least | Foreign CO₂, at most |
|---|---|---|
| Each storage licence | 70 | 30 |
How much can be stored
Estimates differ widely, because they count different rock and use different methods:
- Low
- High
Show data
| Item | Low | High |
|---|---|---|
| Government-linked estimate | 80 | 400 |
| Saline aquifers only (ExxonMobil) | 80 | 200 |
| Upper estimates cited | 400 | 600 |
Even the lowest figure is many decades of Indonesia’s own emissions. Capacity is not the constraint. Cost, monitoring and contracts are.
What exists today
The flagship is BP’s Tangguh CCUS project in West Papua, which reinjects CO₂ from the Tangguh LNG plant. Reported targets range from about 1.8 million tonnes a year to 15 million tonnes in an initial phase, with start dates that differ between sources. Tangguh became the first CCUS project registered under the Indonesia–Japan Joint Crediting Mechanism.
Cross-border storage is further behind. Japan, South Korea and Singapore have signed memoranda, but no binding agreements for shipping CO₂ to Indonesia were in place as of 2026.
What it means for the power sector
CCS is sometimes presented as a way to keep coal plants running. For power generation that is a hard case: capture equipment is expensive, uses a large share of a plant’s own output and must run for decades. Solar plus storage and other clean sources are usually cheaper ways to cut power-sector emissions.
CCS is more useful where alternatives are scarce: gas processing, cement, fertiliser and some chemicals. That is where Indonesia’s hub would earn its keep, and where engineering work on capture, transport and monitoring will concentrate.
What to watch
- Final investment decisions on Tangguh’s expansion and any second project.
- The first binding cross-border CO₂ storage contract.
- Monitoring, reporting and verification rules for stored CO₂.
Sources
- Norton Rose Fulbright, understanding carbon capture and storage in Indonesia
- ERIA, is Indonesia’s ambition to become an international CCUS hub attainable?
- SUPRA International, Indonesia CCS development: regulatory framework and storage capacity
- Industry Asia Pacific, IICCS Forum 2026 positions Indonesia as regional CCS hub
- USEA, Indonesia’s CCUS strategy
Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.