Indonesia’s first nuclear plant, on paper
RUPTL 2025–2034 includes Indonesia’s first nuclear capacity, two 250 MW units in Sumatra and Kalimantan by 2034, with talk of 7 GW by 2040. Nuclear plants take 10 to 13 years to deliver. What is decided and what is not.
Key points
- RUPTL includes 500 MW of nuclear, two 250 MW units, by 2032–2034.
- Government modelling points to 7 GW of nuclear by 2040.
- PLN estimates 10 to 13 years from design to commissioning.
For the first time, PLN’s electricity plan includes nuclear power. The commitment is small; the ambition around it is larger.
- 500 MWTwo 250 MW units in RUPTL, 2032–2034
- 7 GWGovernment modelling for 2040
- 10–13 yrsPLN’s estimate from design to commissioning
What the plan says
RUPTL 2025–2034 includes 500 MW: two 250 MW units, one in the Sumatra grid and one in Kalimantan, to be completed no later than 2034. Reporting describes small modular reactor (SMR) technology, and the government is evaluating several vendor proposals. In October 2026, officials said 28 candidate sites were being prepared.
The longer ambition
Government modelling points to about 7 GW by 2040. PLN itself estimates that a nuclear plant takes 10 to 13 years from design to commissioning.
What is still open
- Institutions. The regulator, Bapeten, exists. The Nuclear Energy Programme Implementing Organisation (NEPIO), which coordinates a first programme, had been requested but we found no confirmation it was formally established.
- Technology choice. Several reactor designs are under evaluation; none is licensed in Indonesia.
- Finance and cost. First-of-a-kind SMRs carry cost and schedule risk.
How it fits with solar
Nuclear is firm, low-carbon output, the role coal plays today. It would complement, not replace, solar and storage. On the plan’s timeline, though, nuclear arrives after most of the decade’s solar and storage decisions are made. For the 2020s, the firm clean supply has to come from hydro, geothermal and batteries.
The timing problem
If PLN’s estimate of 10 to 13 years holds, a project starting design in 2026 would commission between 2036 and 2039, later than the RUPTL’s 2032–2034. Demand will not wait: at 5–7% growth a year, consumption could rise by 340–520 TWh by 2035. Whatever nuclear eventually contributes, the next decade’s demand has to be met by sources that build faster. See Indonesia’s electricity demand is growing again.
Sources
- Kontan, Nuclear enters RUPTL 2025–2034: first 500 MW project
- World Nuclear Association, Nuclear power in Indonesia
- Enerdata, Indonesia targets start of first nuclear power plant in 2032
- CNBC Indonesia, Government prepares 28 sites for nuclear projects, October 2026
- Petromindo, PLN targets 7 GW of nuclear capacity by 2040
- SUPRA International, RUKN 2025–2060 national electricity plan
Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.
Satu Energy (PT Satu Solusi Energi), Jakarta. Read online and download the chart data at satuenergy.com/insights/indonesia-nuclear-plan/. Contact: contact@satuenergy.com. This report uses public sources only; figures for plans and programmes are not operating capacity unless stated.