RUPTL 2025–2034 in two charts

PLN’s 2025–2034 electricity plan adds 69.5 GW, 61% renewable and 15% storage. But most fossil capacity comes first and most renewables come after 2030. The plan by technology and by phase.

Download report (PDF)Download data (CSV)
Illustration for RUPTL 2025–2034 in two charts

Key points

  • The plan adds 69.5 GW: 42.6 GW renewable, 10.3 GW storage, 16.6 GW fossil.
  • Solar is the largest single technology at 17.1 GW, followed by hydro at 11.7 GW.
  • 77% of fossil additions come in 2025–2029; 71% of renewables come after 2030.

The RUPTL is PLN’s ten-year electricity supply plan. The 2025–2034 edition adds 69.5 GW of generation and storage. Two views explain most of it: what gets built, and when.

The plan at a glance
  • 69.5 GWNew capacity, 2025–2034
  • 61%Share that is new and renewable
  • Rp 2,967 tnTotal investment
  • 73%Generation investment expected from IPPs
Source: Energy ministry via Republika and Metro TV, 2025Download CSVSatu Energy

By technology

Solar is the largest single addition in the planNew capacity in RUPTL 2025–2034, GW
  • Solar
  • Hydro
  • Wind
  • Geothermal
  • Bioenergy
Solar 17.1 GW
Hydro 11.7 GW
Gas 10.3 GW
Storage (BESS and pumped hydro) 10.3 GW
Wind 7.2 GW
Coal 6.3 GW
Geothermal 5.2 GW
Bioenergy 0.9 GW

Fossil split as reported by one source; others give 9.2 GW gas and 3.5 GW coal for 2025–2030 plus 3.9 GW thermal after 2030. Nuclear (0.5 GW) is counted within the plan’s new-energy total.

Source: ESDM and PLN via Argus, Enerdata and TaiyangNews, May 2025Download CSVSatu Energy
Show data
TechnologyGW
Solar17.1
Hydro11.7
Gas10.3
Storage (BESS and pumped hydro)10.3
Wind7.2
Coal6.3
Geothermal5.2
Bioenergy0.9

Renewables total 42.6 GW (61%), storage 10.3 GW (15%) and fossil 16.6 GW (24%). The plan also includes two 250 MW nuclear units, in Sumatra and Kalimantan, by 2034.

By phase

Fossil comes first, renewables come laterCapacity additions by phase and type, GW
2025–2029 fossil 12.7 GW
2025–2029 renewables 12.2 GW
2025–2029 storage 3.0 GW
2030–2034 fossil 3.9 GW
2030–2034 renewables 30.4 GW
2030–2034 storage 7.3 GW

Renewables shown in the solar colour as a group; they include hydro, wind, geothermal and bioenergy.

Source: ESDM and PLN via Hogan Lovells and Argus, 2025Download CSVSatu Energy
Show data
Phase and typeGW
2025–2029 fossil12.7
2025–2029 renewables12.2
2025–2029 storage3.0
2030–2034 fossil3.9
2030–2034 renewables30.4
2030–2034 storage7.3

The first phase totals 27.9 GW and is almost evenly split between fossil and renewables. The second phase, 41.6 GW, is overwhelmingly renewable. In other words, 77% of the plan’s fossil capacity is scheduled before 2030, and 71% of its renewables after.

Why the timing matters

Back-loading renewables is a common planning choice: transmission, procurement and storage take time. It also concentrates risk. If grid projects such as the Green Enabling Super Grid slip, the 2030s renewable wave slips with them, while the 2020s fossil additions are already locked in.

The 100 GWp question

The RUPTL’s 17.1 GW of solar is far below the 100 GWp programme. Until a revised plan reflects that target, developers should treat RUPTL figures as what PLN has committed to plan for, and 100 GWp as a political target still being translated into projects.

Who is meant to build it

The plan expects independent power producers to fund about 73% of generation investment, Rp 1,566.1 trillion, covering about 50.7 GW. That turns the RUPTL from a PLN building plan into a procurement plan: its delivery depends on tenders, contracts and bankability, not only on PLN’s balance sheet.

Private producers carry most of the generation billGeneration investment, Rp trillion
01,0002,0003,000
+1,566.1IPPs
+567.6PLN and others
2,133.7Generation total
Source: Metro TV and Tirto, citing the energy ministry; PLN share by subtractionDownload CSVSatu Energy
Show data
StepRp tn
IPPs1,566.1
PLN and others567.6
Generation total2,133.7

More on the money in the RUPTL investment bill, and on the gas inside the plan in the 10 GW of gas.

Sources

  1. Argus Media, Indonesia to add 69.5 GW of power capacity over 2025–34
  2. Enerdata, Indonesia aims to add 69.5 GW of new power capacity between 2025 and 2034
  3. Hogan Lovells, Powering Indonesia’s future: key takeaways from the 2025–2034 RUPTL
  4. TaiyangNews, Indonesia to add 42.6 GW renewables by 2034 under RUPTL
  5. Metro TV, government targets 73% of RUPTL generation investment from private sector
  6. Republika, RUPTL 2025–2034 opens an investment opportunity of Rp 2,967 trillion

Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.