Can Indonesia make its own solar panels?
Indonesia has about 10.9 GW a year of solar module capacity across 34 makers, with local content of 40 to 55%. Cell capacity is far smaller but growing fast. What TKDN rules mean for 100 GWp project costs.
Key points
- 34 domestic makers produce up to about 10.9 GW of modules a year.
- Local content in modules averages 40 to 55%; the project minimum is 20%.
- Announced cell plants (1, 2 and 7.5 GW) would narrow the gap to modules.
The 100 GWp programme is framed around energy independence, including a domestic supply chain. How much of the hardware can Indonesia make?
- 10.9 GWModule capacity a year
- 4.3 GWOf it geared to export
- 1.5–1.9 GWProjected domestic demand a year
- 7.5 GWNew TOPCon cell plant, November 2026
Modules: enough for the first wave
A May 2026 count found 34 domestic module makers with about 10.9 GW of annual capacity. An SMM analysis puts total module capacity higher, at about 27 GW, likely counting announced and export-oriented lines. Both are large next to the first wave of tenders.
Cells: the bottleneck
A module is assembled from cells, and most of Indonesia’s cells are imported. That is changing:
What TKDN means for projects
TKDN is Indonesia’s local-content rule. The minimum for solar projects is 20%, which still permits imported modules. Domestic modules carry about 40 to 55%. Some government and PLN projects are moving to stricter TKDN rules in 2026, which favour local supply.
For developers, that shifts three things:
- Price. Local modules may cost more than imports, at least while cell capacity ramps up.
- Bankability. Lenders will look at the warranty strength and track record of new local makers.
- Schedule. If many projects need compliant modules at once, supply becomes the critical path.
After the US duties
In September 2026 the US finalised antidumping and countervailing duties on Indonesian cells, with combined rates from about 168% to 268%. About 4.3 GW of module capacity was geared to export. That output now needs a domestic home, and domestic demand is projected at only 1.5–1.9 GW a year. More in US duties close a door.
- Geared to export
- Other capacity
Show data
| Item | Geared to export | Other capacity |
|---|---|---|
| 2026 | 4.3 | 6.6 |
For buyers, oversupply means stronger negotiating power on price and TKDN-certified products, but also more reason to audit factories and test batches before shipment.
What to watch
- Final TKDN thresholds in the Mentari Nusantara documents.
- Ramp-up of the new cell plants.
- Export pressure: high US tariffs on Southeast Asian modules push makers toward the domestic market.
Sources
- Petromindo, Indonesia’s solar module capacity reaches 10.9 GW per year
- SMM, Indonesia’s first 30 GW solar tender nears: storage, grid and local content
- PV Tech, Yingfa Ruineng launches 7.5 GW TOPCon cell plant in Indonesia
- Investor Trust, Trina Mas Agra injects US$100 million into Indonesian factory
- Petromindo, LONGi–PNRE module plant to start operations in early 2026
- Ecobiz Asia, APAMSI: Indonesia’s solar manufacturing capacity reaches 10.9 GW
- pv-tech, US finalises AD/CVD duties on solar cells from India, Indonesia and Laos
Summaries and analysis by Satu Energy. Programme and plan figures are not operating capacity unless stated.
Satu Energy (PT Satu Solusi Energi), Jakarta. Read online and download the chart data at satuenergy.com/insights/indonesia-solar-manufacturing-tkdn/. Contact: contact@satuenergy.com. This report uses public sources only; figures for plans and programmes are not operating capacity unless stated.